The Campus Construction Update is a regular feature of the Weekly E-Bulletin in an effort to keep the campus community informed of any potential distruptions to regular work practices during summer construction.
Week of May 29th
Piping installation to continue in Chute, Boulden, Ruminant Animal Centre, Langille buildings and start in Haley and Jenkins Hall Buildings. (chance of minor noise with this work)
Civil work for concrete pads in Chute, Boulden, Ruminant, Langille, Haley and Jenkins Hall Buildings.
Electrical work to begin in Haley building. (Chance of minor noise with this work, hammer drilling)
Week of June 5th
Piping installation to continue in Langille, Haley and Jenkins Hall Buildings. (chance of minor noise with this work)
Civil work for concrete pads in Chute, Boulden, Ruminant, Langille, Haley, and Jenkins Hall Buildings.
Electrical work to continue in Haley building. (Chance of minor noise with this work, hammer drilling)
Any questions or concerns please contact:
Stephanie MacKenzie
Project Manager Facilities Management
902.956.4492
Stephanie.Mackenzie@dal.ca
Recent News
- DPMG Winter Warm up Party
- Apuknajit Mid‑Winter Feast
- Meat Sale
- Photo Contest ‑ International Development Week 2026
- Calling all PhD students: Become an OpenThinker!
- ACORN In Good Hands Conference
- AC Bookstore Closing Jan. 30 — Reopening in August
- Sustainable Development Goals (SDGs) Expo