Dentistry Clinic and Facilities Renewal Weekly Look Ahead (August 19th)

Posted by Admin on August 19, 2016 in Dentistry Renewal, News

Information Item: All ICP barriers are in place and the required negative air pressure required by the ICP plan is being monitored. Pressure to be monitored continuously throughout construction and ICP consumables (filters, sticky mats, etc.) to be changed as necessary.

PHASE 1

Level 1 MDR

-          MDR was handed over Monday

PHASE 2

Lvl 1 PH 2.1 & 2.2 North Clinic

-          Northeast Mechanical and Electrical ceiling rough-ins are ongoing

-          Steel stud is ongoing. Drywall first side is scheduled to start August 23rd

Lvl 2 PH 2.2 North Clinic

-          Mechanical and Electrical ceiling rough-ins are ongoing

-          Scanning for cores is ongoing. Core drilling is ongoing

-          Steel stud is ongoing. Drywall first side is scheduled to start September 9th

-          Door frames are being stood

-          IC walls and ante room for new layout are in place

Penthouse

-          Rough-ins are ongoing for the new heating and medical gas services

Lvl 1 PH 2.4 Corridor

-          Lvl 1 Corridor was handed over Monday

Lvl 2 PH 2.4 Corridor

-          Corridor work is complete at Dispensaries. Ceiling will be tiled in outside of FM offices next week

Shutdowns Next Week

1.       Fire alarm shutdown Monday August 22nd at 11:00am

General Items

- Infection control is being monitored 24/7 to ensure there is no contamination to adjacent areas.