CHEB Update: Rock Breaking West Entrance Driveway

Posted by Admin on August 17, 2015 in News, Notices and Alerts, Campus Development, CHEB

Please note the change in dates from Aug 17 to Aug 20 due to construction delays. 

When:

  • Starting Mon Aug 20 approximately 12:00 noon – possibly earlier
  • Then daily starting at 7:00 am to 5:00 pm through to Aug 24
  • Work will take 4 or 5 days to complete

What and Where:

  • Rock breaking and removal for entrance driveway off University Ave on west side of CHEB building
  • Work is required for new retaining wall and re-grading of sub-grade the driveway

Impacts:

  • Noise from rock breaking machinery
  • Bird Construction does not anticipate any impact on use of the LSRI parking garage
  • Rock breaking will not take place during class time so as to minimize disruption.

 

We apologize for any inconvenience this necessary work may cause. If you have any questions or concerns please contact Project Manager, Michael Eakin at 902-462-6545.