1.  Roof Membrane and Exterior Walls

Roof work (including skylight installation) and installation of exterior siding is weather dependent and has been proceeding.  Installation of exterior glazing is complete. Installation of green roof materials, roof top fence and exterior wall system will continue during August.

2.  Wall Partitions

Interior partitions, including gypsum board is complete.  Interior painting has started.  Interior glazing and doors has begun.   

3.  Mechanical/Electrical Work

Plumbing, heating, ventilation and electrical installations continue.

4.  Landscaping

Rough grading and light bases are complete.  Curbs and sidewalks have begun.  

 

For any issues that may arise during the course of this work, please contact Director of Capital Projects, Alex Walker at 902-494-1071.