CHEB Update: Installation of Compressed Air Line in LSRI Parking Garage

Posted by Admin on July 21, 2015 in News, Notices and Alerts, Campus Development, CHEB

When:

  • Starting Wed Jul 22 at 6:30 am
  • Work will take 3 or 4 days on and off – work will not be continuous

What and Where:

  • Installation of compressed air line in the LSRI Parking Garage
  • Lines will be run along the underside of the concrete slab above using existing pipe hangers as much as possible

Impacts:

  • Bird Construction does not anticipate any impact on parking garage users
  • Work will start early at 6:30 am ahead of when most garage users arrive
  • If and when any parking garage users require access to parking spots in the vicinity of the work – the work will cease for the day
  • The parking garage will remain open – workers will monitor pedestrian and vehicle traffic
 
We apologize for any inconvenience this necessary work may cause. If you have any questions or concerns please contact Project Manager, Michael Eakin at 902-462-6545.