1. Roof Membrane and Exterior Walls

Roof membrane work and installation of exterior wall materials is weather dependent and has been proceeding.  Installation of exterior window frames and roof membrane will occur over the next few weeks.

2. Wall Partitions

Installation of steel studs for interior partitions is 100% complete.  Gypsum board installation will begin next week.

3. Mechanical/Electrical Work

Plumbing, heating, ventilation and electrical installations are in progress.

 

For any issues that may arise during the course of this work, please contact Director of Capital Projects, Alex Walker at 902-494-1071.