Construction Schedule

Steele Ocean Sciences Building

 

February 2012

  • Begin constructing the building’s structural and miscellaneous metals

March 2012

  • Complete the building’s concrete structure
  • Begin masonry

April 2012

  • Begin the building’s rough carpentry
  • Complete constructing the building’s structural and miscellaneous metals

May 2012

  • Complete the building’s rough carpentry
  • Begin the roofing and waterproofing process
  • Begin glazing and the construction of metal panels, doors, and frames
  • Begin to put in elevators and platforms
  • Begin mechanical and electrical work

July 2012

  • Complete the roofing and waterproofing process

August 2012

  • Begin with finishes

October 2012

  • Elevators and platforms put up
  • Complete glazing and the construction of metal panels, doors, and frames

November 2012

  • Begin working on the building’s specialties

December 2012

  • Complete finishes

January 2013

  • Complete masonry

February 2013

  • Permanent power connection
  • Building elevator licensed

March 2013

  • Complete mechanical and electrical rough in
  • Achieve dust free environment
  • Initiate building commissioning activities

April 2013

  • Complete finishes
  • Complete building specialties
  • Complete tenant fit-up
  • Complete final construction cleaning
  • Construction substantial completion

May 2013

  • Complete final commissioning activities
  • Construction completion (May 20, 2013)
  • Occupancy and tenant moves initiated

June 2013

  • Complete post occupancy evaluation