Construction Schedule

LeMarchant Place

 

December 2011

 

  • Building design is substantially completed
  • Erect demolition site fencing and signage
  • Abatement and demolition of existing houses
  • Modifications to Memorial Arena exits
  • Construction site offices open

January 2012

 

  • Complete demolition of the existing houses
  • Complete modifications to arena exits
  • Erect main construction site fencing and signage
  • Begin excavation and site services

February 2012 - March 2013

  •  Construct the building’s concrete structure

January 2013 - June 2013

 

  •  Building envelope – siding and roofing and windows

November 2012 - March 2014

 

  • Plumbing, ventilation and electrical services throughout the building
  • Interior partitions, ceilings, doors and hardware
  • Interior finishes - flooring painting, cabinetwork
  • Major equipment installations
  • Elevators

April 2014

 

  • Substantially complete

June 2014

 

  • Begin Commissioning

July-August 2014

 

  • Furniture and equipment