Construction Schedule

 

December 2011

 

  • Building design is substantially completed
  • Erect demolition site fencing and signage
  • Abatement and demolition of existing houses
  • Modifications to Memorial Arena exits
  • Construction site offices open

January 2012

 

  • Complete demolition of the existing houses
  • Complete modifications to arena exits
  • Erect main construction site fencing and signage
  • Begin excavation and site services

February 2012 - November 2012

 

  •  Begin work on foundations 
  •  Construct the building’s concrete structure

August 2012 - May 2013

 

  •  Building envelope – siding and roofing and windows

August 2012 - August 2013

 

  • Plumbing, ventilation and electrical services throughout the building
  • Interior partitions, ceilings, doors and hardware
  • Interior finishes - flooring painting, cabinetwork
  • Furniture and equipment
  • Commissioning

September 2013

 

  • Open for students

 

Last updated - January 5, 2012