Construction Schedule
December 2011
- Building design is substantially completed
- Erect demolition site fencing and signage
- Abatement and demolition of existing houses
- Modifications to Memorial Arena exits
- Construction site offices open
January 2012
- Complete demolition of the existing houses
- Complete modifications to arena exits
- Erect main construction site fencing and signage
- Begin excavation and site services
February 2012 - November 2012
- Begin work on foundations
- Construct the building’s concrete structure
August 2012 - May 2013
- Building envelope – siding and roofing and windows
August 2012 - August 2013
- Plumbing, ventilation and electrical services throughout the building
- Interior partitions, ceilings, doors and hardware
- Interior finishes - flooring painting, cabinetwork
- Furniture and equipment
- Commissioning
September 2013
Last updated - January 5, 2012